❄️ HVAC

Chiller Tonnage Calculator – Chiller Sizing & TR Calculation (BTU)

Free chiller tonnage calculator: chiller sizing, TR calculation and BTU/kW cooling load for AHRI-rated chillers. Formula + example. No sign-up.

📐 Standard: ASHRAE / AHRI
✅ Free to use
📄 PDF export
📱 Mobile friendly
❄️
Chiller Tonnage Calculator Calculator
Reference: ASHRAE / AHRI
❄️ HVAC
Free chiller tonnage calculator: chiller sizing, TR calculation and BTU/kW cooling load for AHRI-rated chillers. Formula + example. No sign-up.
Inputs
Results
Calculation confidence: Planning-levelSuitable for early design, estimating and feasibility checks. Verify the final design against the governing code and a licensed engineer before construction or procurement.
Was this helpful?
💬 Suggest an improvement

About This Calculator

A chiller is the heart of a central HVAC system - it produces chilled water that is distributed to AHUs and fan coil units throughout the building. Selecting the correct chiller tonnage is critical: undersizing means the building cannot be cooled; oversizing means the chiller cycles on and off, reducing efficiency and increasing maintenance costs. 1 TR (ton of refrigeration) = 3.517 kW of cooling.

AHRI Standard 550/590 governs chiller rating conditions. Air-cooled chillers are rated at 35°C ambient; water-cooled at 29°C entering condenser water. IPLV (Integrated Part Load Value) is the weighted average efficiency over a full operating season - more important than full-load efficiency for US buildings where the chiller runs at part load for most of the year. DOE (Bureau of Energy Efficiency) star ratings for chillers are based on IPLV.

Chiller Sizing Formula

ASHRAE / AHRI

Cooling Capacity: TR = Total Cooling Load (kW) / 3.517 or TR = Total Cooling Load (BTU/hr) / 12,000 Chiller kW Input: kW_input = TR × 3.517 / COP Typical COP: Air-cooled: 2.8–3.5 | Water-cooled: 4.5–6.5 Chilled Water Flow: Q_chw (L/s) = Cooling (kW) / (ρ × Cp × ΔT) = kW / (4.187 × 5) [for 7/12°C CHW system] Condenser Water Flow (water-cooled): Q_cw = (Cooling kW + Compressor kW) / (4.187 × 5) [for 29/34°C CW]

Worked Example

An office building has a calculated cooling load of 350 kW. Chiller capacity required: TR = 350 / 3.517 ≈ 99.5 TR - select a 100 TR chiller.

For a water-cooled chiller with COP 5.5: Input power = 100 × 3.517 / 5.5 ≈ 64 kW. Chilled water flow at 7/12°C (ΔT = 5°C): Q_chw = 350 / (4.187 × 5) ≈ 16.7 L/s. Condenser water flow: Q_cw = (350 + 64) / (4.187 × 5.5) ≈ 18 L/s - this sizes the condenser pump and cooling tower selection.

Chiller Tonnage & Chilled-Water Reference (ASHRAE)

How the Chiller Tonnage Calculator Works

A chiller is sized in tons of refrigeration, and getting that number right sets the entire chilled-water plant — the chiller, the pumps, the piping and the cooling tower. This calculator converts a building's cooling load to chiller tons and computes the associated chilled-water flow and power using the standard ASHRAE relationships. One ton equals 12,000 BTU/hr (3.517 kW), so the tons follow directly from the cooling load; the chilled-water flow follows from the flow-temperature relationship (about 2.4 GPM per ton at a 10°F ΔT); and the power follows from the chiller's efficiency in kW per ton. Enter the load, the chilled-water temperature difference and the efficiency, and the tool returns the required tonnage, the design flow in GPM and the electrical demand — the numbers that anchor a complete plant design.

The Chiller Sizing Formulas

  • Tonnage: Tons = cooling load (BTU/hr) ÷ 12,000
  • Chilled-water flow: GPM = (Tons × 12,000) ÷ (500 × ΔT) = Tons × 24 ÷ ΔT
  • Condenser-water flow (water-cooled): ≈ 3 GPM per ton (rejects ~15,000 BTU/hr/ton)
  • Chiller power: kW = Tons × (kW/ton efficiency)

The constant 500 in the flow equation is 60 min/hr × 8.33 lb/gal × 1 BTU/lb·°F for water, so at the common 10°F chilled-water ΔT the flow is exactly 2.4 GPM per ton. The kW/ton figure captures efficiency — water-cooled centrifugal chillers reach 0.5–0.6 kW/ton, while air-cooled units run 1.0–1.2 kW/ton — and it, not the tonnage, drives the operating cost.

Variable & Unit Reference

SymbolQuantityUS UnitSI Unit
TonsCooling capacitytons (12,000 BTU/hr)kW
QCooling loadBTU/hrkW
GPMChilled-water flowGPML/s
ΔTCHW temperature diff°F°C
kW/tonEfficiencykW/tonCOP
IPLVPart-load efficiencykW/ton

Unit handling: US HVAC uses tons, BTU/hr, GPM and °F — exactly what this calculator uses. Conversions: 1 ton = 12,000 BTU/hr = 3.517 kW, 1 GPM = 0.0631 L/s, ΔT°F = 1.8 × ΔT°C. Efficiency crosses over as kW/ton = 3.517 ÷ COP, so 0.6 kW/ton equals a COP of about 5.9.

Step-by-Step Chiller Sizing

  1. Determine the peak cooling load in BTU/hr from a Manual N / ASHRAE load calculation.
  2. Convert to tons by dividing by 12,000, and add a modest margin (10–15%) or use diversity for a central plant serving many zones.
  3. Choose the chilled-water ΔT (10–16°F) and compute the design flow in GPM.
  4. Select the chiller type — air-cooled or water-cooled — based on plant size, water availability and efficiency goals.
  5. Estimate power from the efficiency (kW/ton) and check the electrical service.
  6. Size the balance of plant — pumps to the flows, cooling tower to the heat rejection, and piping to the velocities.

Worked Example 1 — 100-Ton Air-Cooled Office Chiller

An office has a 1,200,000 BTU/hr peak cooling load, served by an air-cooled chiller with 44°F/54°F chilled water (ΔT = 10°F) at 1.1 kW/ton.

  1. Tonnage: 1,200,000 ÷ 12,000 = 100 tons.
  2. Chilled-water flow: 100 × 24 ÷ 10 = 240 GPM.
  3. Power: 100 × 1.1 = 110 kW (about 133 A at 480 V, 3-phase).
  4. Plant: a 240 GPM primary pump and 4-inch chilled-water mains; no cooling tower (air-cooled).

Answer: a 100-ton air-cooled chiller, 240 GPM, ~110 kW. Air-cooled units are simple (no tower or condenser water) but less efficient, which is why they suit smaller plants where the energy penalty is acceptable.

Worked Example 2 — 500-Ton Water-Cooled Plant

A large building has a 500-ton load served by a water-cooled centrifugal chiller with a 12°F chilled-water ΔT at 0.55 kW/ton.

  1. Chilled-water flow: 500 × 24 ÷ 12 = 1,000 GPM.
  2. Condenser-water flow: 500 × 3 = 1,500 GPM to the cooling tower.
  3. Heat rejection: 500 × 15,000 = 7,500,000 BTU/hr (625 tons of tower).
  4. Power: 500 × 0.55 = 275 kW — roughly half the energy of an equivalent air-cooled plant.

Answer: a 500-ton water-cooled plant, 1,000 GPM chilled + 1,500 GPM condenser water, ~275 kW. The higher ΔT cuts the chilled-water flow (and pump energy), and the water-cooled cycle roughly halves the chiller power — the reasons large plants are water-cooled.

Standards & Code References

  • ASHRAE Handbook — HVAC Systems & Equipment — chiller and chilled-water plant design.
  • ASHRAE 90.1 — minimum chiller efficiency (kW/ton and IPLV) by type and size.
  • AHRI Standard 550/590 — chiller performance rating (full- and part-load, IPLV).
  • ASHRAE 15 — safety code for refrigeration systems (machinery room, refrigerant).
  • ASHRAE 34 — refrigerant designations and safety classifications.
  • CTI — cooling-tower thermal performance certification.

Key Facts to Remember

  • One ton of cooling = 12,000 BTU/hr = 3.517 kW — the master conversion.
  • Chilled-water flow ≈ 2.4 GPM/ton at 10°F ΔT; a higher ΔT means less flow and less pump energy.
  • Water-cooled condenser flow ≈ 3 GPM/ton, rejecting ~15,000 BTU/hr per ton.
  • kW/ton is the efficiency metric: 0.5–0.6 water-cooled, 1.0–1.2 air-cooled.
  • IPLV/IEER matters more than full-load efficiency because chillers spend most hours at part load.
  • Higher chilled-water ΔT (14–16°F) is a low-cost efficiency win — less flow, smaller pumps and pipes.
  • Air-cooled avoids a tower and water use; water-cooled is more efficient for larger plants.
  • Size the plant to the coincident peak with diversity, and stage multiple chillers for part-load efficiency.

Chiller Types & Efficiency (the "money table")

Chiller TypeTypical kW/tonSize Range (tons)Best For
Air-cooled scroll1.0–1.310–200Small plants, no water
Air-cooled screw0.9–1.1150–500Mid-size, no tower
Water-cooled scroll0.7–0.920–200Small water-cooled
Water-cooled screw0.6–0.75150–800Mid-large plants
Water-cooled centrifugal0.5–0.62200–3,000+Large plants
Absorption (gas/steam)100–1,500Waste heat, gas rate

Flow reference: at 10°F ΔT = 2.4 GPM/ton, at 12°F = 2.0 GPM/ton, at 16°F = 1.5 GPM/ton (chilled water); condenser water ≈ 3 GPM/ton. Rules of thumb: office ~300–400 ft²/ton, retail ~250–350, restaurant ~100–150.

Real-World Applications

  • Commercial office central chilled-water plants.
  • Hospitals and healthcare with high, continuous cooling.
  • Data centers with year-round IT cooling loads.
  • Hotels, malls and mixed-use developments.
  • Universities and district cooling plants.
  • Industrial process cooling and manufacturing.
  • Cold storage and food processing.
  • Cleanrooms and laboratories.

Common Mistakes

  • Oversizing the chiller, which hurts part-load efficiency and shortens compressor life.
  • Ignoring IPLV, selecting on full-load kW/ton when the plant runs mostly at part load.
  • Designing low chilled-water ΔT, forcing high flow, big pumps and low delta-T syndrome.
  • Forgetting condenser water and tower sizing for water-cooled plants.
  • Summing zone peaks without diversity for a central plant.
  • Overlooking the electrical demand of a large chiller.
  • Single chiller with no staging for varying load and redundancy.
  • Neglecting refrigerant phase-out and code (ASHRAE 15/34, refrigerant transitions).

Air-Cooled vs Water-Cooled

The most fundamental chiller decision is air-cooled versus water-cooled, and it trades first cost and simplicity against efficiency and water use. Air-cooled chillers reject heat directly to the atmosphere through condenser coils and fans, so they need no cooling tower, condenser-water pumps, or water treatment — a self-contained, lower-first-cost, easier-to-maintain package usually mounted outdoors. Their penalty is efficiency: rejecting heat to hot ambient air rather than to evaporatively cooled water means they run at 1.0–1.3 kW/ton, so they cost more to operate. They suit smaller plants (up to a few hundred tons) and sites where water is scarce or a tower is impractical. Water-cooled chillers reject heat to condenser water that is then cooled in a cooling tower by evaporation, reaching much lower condensing temperatures and therefore much better efficiency — 0.5–0.75 kW/ton — but at the cost of the tower, condenser pumps, water treatment, water consumption and more maintenance. They dominate larger plants (500+ tons) where the energy savings justify the added infrastructure. The crossover depends on plant size, hours of operation, energy and water rates, and space — but as a rule, small and intermittent plants favor air-cooled simplicity, while large and continuously operating plants favor water-cooled efficiency. This calculator handles both; the type sets the efficiency and whether a tower and condenser loop are part of the design.

Efficiency: kW/ton, COP & IPLV

Chiller efficiency is expressed several ways, and understanding them prevents costly selection errors. kW/ton is the US standard — the electrical power drawn per ton of cooling, where lower is better; it converts to COP (coefficient of performance) as COP = 3.517 ÷ kW/ton, so 0.6 kW/ton equals a COP of about 5.9. But full-load efficiency tells only part of the story, because a chiller almost never runs at 100% load — the building's cooling demand varies with weather and occupancy, so the machine spends most of its hours at part load. That's why the IPLV (Integrated Part-Load Value), defined by AHRI 550/590, is often the more meaningful number: it weights efficiency across 100%, 75%, 50% and 25% load points to represent typical operation. A chiller with excellent full-load kW/ton but poor part-load performance can cost more to run than one with modestly lower peak efficiency but strong part-load numbers. Variable-speed drives on the compressor dramatically improve part-load efficiency, which is why VSD centrifugal chillers achieve excellent IPLVs. ASHRAE 90.1 sets minimum full-load and IPLV efficiencies by type and size. When you select a chiller, look at both the full-load kW/ton and the IPLV, and weight the IPLV heavily for any plant that operates across a range of loads — which is essentially all of them.

Chilled-Water ΔT & Low Delta-T Syndrome

The chilled-water temperature difference (ΔT) is a powerful and underused design lever. Because flow is inversely proportional to ΔT (GPM = tons × 24 ÷ ΔT), raising the design ΔT from the traditional 10°F to 14–16°F cuts the chilled-water flow by 30–40%, which shrinks the pumps, the pipe sizes and the pump energy — a substantial capital and operating saving for essentially no cost, just a design choice paired with coils selected for the higher ΔT. However, many plants suffer from low delta-T syndrome, where the actual return-water temperature is lower than design (the ΔT collapses), forcing more flow to deliver the same cooling and defeating the intended savings. Its causes include oversized or fouled coils, improper control-valve selection (three-way valves that bypass, or two-way valves that don't modulate well), incorrect setpoints, and low-load bypass. The consequence is that pumps run harder, a second chiller may start unnecessarily, and plant efficiency drops. Preventing it requires coils and control valves designed for the target ΔT, proper variable-flow controls, and commissioning to verify the ΔT holds across the load range. When you size a chiller and its flow, choosing a higher ΔT is a smart efficiency move — but only if the whole system is designed and commissioned to actually achieve and maintain it, or the promised savings evaporate into low-delta-T pumping.

Condenser Water & Cooling Towers

For water-cooled plants, the condenser-water loop and cooling tower are integral to the design and to the efficiency the chiller can achieve. The chiller rejects both the cooling load and the work of compression to the condenser water — about 15,000 BTU/hr per ton, or roughly 3 GPM per ton of condenser flow — which the cooling tower then rejects to the atmosphere by evaporating a small fraction of the water. The tower is sized to the heat rejection (a "cooling-tower ton" is 15,000 BTU/hr, larger than a chiller ton) and to the local design wet-bulb temperature, which sets how cold the condenser water can get; colder condenser water directly improves chiller efficiency, so a generously sized tower and a low approach temperature pay back in chiller energy. The condenser loop also needs pumps sized to the 3 GPM/ton flow, water treatment to control scale, corrosion and biological growth (including Legionella management), and make-up water for evaporation, drift and blowdown. Modern designs use condenser-water reset and variable-speed tower fans to optimize the trade-off between tower fan energy and chiller energy across conditions. When you size a water-cooled chiller, remember the plant is a system: the chiller efficiency you assume depends on the tower delivering cold condenser water, so the tower, condenser pumps and water treatment must be designed together with the chiller, not as afterthoughts.

Design Tips from the Field

  • Select on IPLV, not just full-load kW/ton — chillers run mostly at part load.
  • Use a higher chilled-water ΔT (14–16°F) to cut flow, pump size and energy.
  • Design coils and valves for the ΔT and commission it to avoid low delta-T syndrome.
  • Stage multiple chillers for part-load efficiency and redundancy rather than one large machine.
  • For water-cooled, design the tower and condenser loop together and use condenser-water reset.
  • Don't oversize — right-size to the coincident peak with modest margin and let staging handle variation.

Quick Reference Summary

To size a chiller: divide the cooling load in BTU/hr by 12,000 to get tons, then compute chilled-water flow as GPM = tons × 24 ÷ ΔT (2.4 GPM/ton at 10°F, 1.5 at 16°F) and power as tons × kW/ton (0.5–0.6 water-cooled, 1.0–1.2 air-cooled). Water-cooled plants add ~3 GPM/ton of condenser water and a cooling tower rejecting ~15,000 BTU/hr per ton. As worked cases: a 100-ton air-cooled office needs 240 GPM and ~110 kW; a 500-ton water-cooled plant needs 1,000 GPM chilled + 1,500 GPM condenser water and ~275 kW. Select on IPLV rather than full-load efficiency, favor a higher chilled-water ΔT to shrink flow and pumps (while designing coils and valves to hold that ΔT), stage multiple chillers for part-load and redundancy, and for water-cooled plants design the tower and condenser loop together. This calculator gives the tonnage, flow and power; the type selection, efficiency optimization and balance-of-plant complete the chilled-water design.

Refrigerants & Environmental Regulations

Chiller selection is increasingly shaped by refrigerant regulation, which directly affects the equipment available and its future serviceability. The industry has moved through generations of refrigerants driven by environmental rules: from ozone-depleting CFCs and HCFCs (R-22, now phased out) to HFCs (R-134a, R-410A) with high global-warming potential (GWP), and now toward low-GWP alternatives (R-1234ze, R-513A, R-32, R-514A and others) under the US AIM Act and EPA rules that are phasing down HFCs. This matters for sizing and selection because the refrigerant affects efficiency, the compressor and machine design, safety classification (ASHRAE 34 flammability and toxicity classes), and machinery-room requirements (ASHRAE 15 for ventilation, detection and relief). Some low-GWP refrigerants are mildly flammable (A2L class), triggering additional safety provisions. Choosing a chiller today means considering not just first-cost efficiency but the refrigerant's regulatory trajectory — a machine using a refrigerant slated for phase-down may face rising service costs and limited future support. This calculator sizes the tonnage and power regardless of refrigerant, but the equipment selection should weigh the refrigerant's GWP, safety class and regulatory status alongside efficiency, because the refrigerant landscape is changing quickly and affects the chiller's whole service life.

Free Cooling & Economizers

One of the biggest energy opportunities in chilled-water plants is avoiding running the chiller compressor at all when the weather allows — free cooling. When the outdoor conditions are cold enough, a waterside economizer uses the cooling tower to produce chilled water (via a heat exchanger) without running the chiller, and an airside economizer brings in cool outdoor air directly to cool the space. For year-round loads like data centers in cool or temperate climates, free cooling can eliminate mechanical cooling for hundreds or thousands of hours a year, dramatically cutting energy use — which is why data-center designs in northern climates prize it. Even partial free cooling (pre-cooling the return water before it reaches the chiller) reduces the chiller's work. ASHRAE 90.1 actually requires economizers on many systems above a size threshold. The design implications ripple back to the chilled-water plant: a waterside economizer needs a plate-and-frame heat exchanger and the controls to switch modes, and the plant benefits from a higher chilled-water temperature (which extends the free-cooling hours). When sizing a chiller for a facility with significant cool-weather operating hours, evaluate free cooling early — it doesn't change the peak tonnage this calculator provides, but it can slash the annual energy the chiller actually consumes, sometimes justifying a plant configuration built around maximizing economizer hours.

Limitations & Disclaimer

This calculator provides a professional first-pass chiller tonnage, chilled-water flow and power estimate using standard ASHRAE relationships and typical efficiencies. It does not replace a full building cooling-load calculation, an hour-by-hour energy model, chiller-selection software with manufacturer performance data, or the cooling-tower, pump and refrigerant-safety (ASHRAE 15/34) design. Actual sizing depends on the load profile, diversity, chilled-water temperatures, part-load operation and equipment selection. Confirm the final plant design with detailed calculations and have it prepared by a licensed mechanical engineer.

Frequently Asked Questions

How do I calculate chiller tonnage? +
Divide the building's peak cooling load in BTU/hr by 12,000, since one ton of refrigeration equals 12,000 BTU/hr. For example, a 1,200,000 BTU/hr load is 100 tons. Add a modest margin (10–15%) for a single unit, or apply diversity for a central plant serving many zones. In SI units, divide the load in kW by 3.517. The tonnage then sets the chilled-water flow and the chiller power.
How much chilled water flow does a chiller need? +
Use GPM = tons × 24 ÷ ΔT, where ΔT is the chilled-water temperature difference in °F. At the traditional 10°F ΔT this is 2.4 GPM per ton, so a 100-ton chiller needs 240 GPM. Raising the ΔT to 12°F gives 2.0 GPM/ton and to 16°F gives 1.5 GPM/ton, which cuts flow, pump size and pump energy — a low-cost efficiency improvement if the coils and valves are designed to hold the higher ΔT.
What is a good chiller efficiency (kW/ton)? +
Water-cooled centrifugal chillers achieve 0.5–0.62 kW/ton at full load (the most efficient), water-cooled screw units 0.6–0.75, and air-cooled units 1.0–1.3 kW/ton. Lower is better. But full-load efficiency is only part of the picture — because chillers run mostly at part load, the IPLV (integrated part-load value) is often more important, and variable-speed chillers achieve excellent IPLVs. ASHRAE 90.1 sets minimum full-load and IPLV efficiencies by type and size.
What is the difference between air-cooled and water-cooled chillers? +
Air-cooled chillers reject heat directly to the atmosphere with fans and need no cooling tower, condenser pumps or water treatment — simpler and lower first cost, but less efficient (1.0–1.3 kW/ton), suiting smaller plants or sites without water. Water-cooled chillers reject heat to condenser water cooled in a tower by evaporation, reaching much better efficiency (0.5–0.75 kW/ton) but requiring a tower, condenser pumps, water treatment and water use — favored for larger plants where the energy savings justify the infrastructure.
How many tons of cooling do I need per square foot? +
As a rough rule of thumb, offices run about 300–400 ft² per ton, retail 250–350, restaurants 100–150, and data or server rooms as little as 50–100 ft² per ton because of equipment heat. These figures are for early budgeting only; the actual load depends on glass, occupancy, ventilation and climate, and can vary ±30%. Always confirm the tonnage with a proper ASHRAE or Manual N cooling-load calculation before selecting equipment.
What is IPLV and why does it matter? +
IPLV (Integrated Part-Load Value) is a weighted efficiency that combines a chiller's performance at 100%, 75%, 50% and 25% load, per AHRI 550/590. It matters because a chiller almost never runs at full load — the cooling demand varies with weather and occupancy, so the machine spends most hours at part load. A chiller with great full-load kW/ton but poor part-load performance can cost more to operate than one with a better IPLV, so IPLV should be weighted heavily in selection.
What is low delta-T syndrome? +
Low delta-T syndrome is when a chilled-water plant's actual temperature difference collapses below design, forcing more flow to deliver the same cooling and defeating the pump-energy savings a high ΔT was meant to provide. Causes include oversized or fouled coils, improper control valves, wrong setpoints and low-load bypass. The result is pumps running harder and chillers starting unnecessarily. Preventing it requires coils and valves designed for the target ΔT, proper variable-flow controls, and commissioning to verify the ΔT holds.
How big a cooling tower does a water-cooled chiller need? +
The tower must reject both the cooling load and the compressor work — about 15,000 BTU/hr per ton, versus the 12,000 BTU/hr of a chiller ton — so a 500-ton chiller needs roughly 625 cooling-tower tons and about 3 GPM per ton of condenser water (1,500 GPM). The tower is sized to the local design wet-bulb temperature, which sets how cold the condenser water can get; colder condenser water improves chiller efficiency, so a generously sized tower with a low approach pays back in chiller energy.
Should I use one large chiller or several smaller ones? +
For most plants, several smaller chillers staged together beat a single large machine. Staging lets the plant match capacity to the varying load by running only the chillers needed, keeping each near its efficient loading, and it provides redundancy — if one chiller fails or is serviced, the others still cool the building. A single large chiller runs inefficiently at low load and leaves no backup. The trade-off is more equipment and controls, justified for any plant where efficiency and reliability matter.
What is free cooling in a chilled-water plant? +
Free cooling avoids running the chiller compressor when the weather is cold enough to cool the water another way. A waterside economizer uses the cooling tower and a heat exchanger to make chilled water without the chiller, and an airside economizer brings cool outdoor air directly into the space. For year-round loads like data centers in cool climates, free cooling can eliminate mechanical cooling for hundreds or thousands of hours a year, cutting energy dramatically. ASHRAE 90.1 requires economizers on many systems above a size threshold.
Is this chiller calculator accurate for design? +
It applies the standard ASHRAE tonnage, flow and power relationships, so it is reliable for preliminary sizing and understanding the plant. A final design requires a full cooling-load calculation, chiller-selection software with manufacturer performance data, an energy model weighing IPLV, and the cooling-tower, pump and refrigerant-safety design — prepared by a licensed mechanical engineer. Confirm the load with a detailed calculation rather than a rule of thumb before selecting equipment.

Related Calculators

Related Articles

🧮 110 Free MEP Calculators

Browse all HVAC, Electrical, Plumbing, Fire, Gas and Mechanical calculators - IS/IBC/ASHRAE compliant, free PDF export.

Browse All Calculators →

⚠️ Disclaimer: For preliminary engineering design only. Verify all results with a licensed engineer before use. Full disclaimer →